The asphalt plant is used to heat and dry the aggregate, sieve it into fractions, weigh these fractions along with the bitumen and filler, and mix them to produce hot asphalt. The appropriate asphalt plant is based on the number of tonnes per hour required by the project, how mobile the plant should be, and how much reclaimed asphalt pavement (RAP) the plant should handle.

Asphalt plants represent major investments and determine the rhythm for every paving machine and roller in the process. This guide shows how the asphalt plant works, what sizing considerations affect it, how Benninghoven TBA, ECO, and RPP plants compare, and what UAE heat means for production.

How an Asphalt Mixing Plant Operates

  • Step 1 – Cold feed bins feeds the aggregate on a collecting belt.
  • Step 2 - Drying drum raises the temperature of aggregate through burner.
  • Step 3 – The hot aggregate is raised on the screen and sorted based on their sizes.
  • Step 4 – Aggregate, filler and bitumen are weighed for batching.
  • Step 5 – Mixer mixes the aggregate to form asphalt.
  • Step 6 - Finished mix goes to a loading silo or straight into trucks.

Plants that reuse RAP add a feed and heating route for recycled material, which reduces the amount of new aggregate and bitumen each tonne needs. Our guide to road recycling explains where RAP comes from.

The Three Decisions That Size an Asphalt Plant

  • Output: match the tonnes per hour production capacity with the paver speed, number of paver teams and haul distance. An overcapacity plant sends the mix to cool in trucks.
  • Mobility: determine whether the plant should be used for many years on one location or moved from project to project. The transportable and module-container designs reduce relocation time.
  • RAP rate: determine the rate of recycled asphalt that will be included in the mix. RAP rates require special plant equipment and save on the use of raw materials.

Storage also matters. The loading silo holds finished mix so the plant keeps producing while trucks queue or the paver pauses, and hot aggregate storage buffers screened aggregate ahead of the mixer.

Benninghoven Asphalt Plants From GENAVCO

Plant Mixing capacity Design focus RAP addition rate Loading silo
Benninghoven ECO 100 to 320 t/h Stationary, container-sized modules for relocation Up to 70% Up to 400 t
Benninghoven TBA 160 to 320 t/h Transportable, semi-mobile or stationary Up to 40% Up to 517 t
Benninghoven RPP 240 to 400 t/h High output with very high recycled content Up to 100% Up to 1,100 t

 

1. Benninghoven TBA Asphalt Mixing Plants

  • Confirmed specification: 4 models with mixing capacities of 160 to 320 t/h, mixer sizes of 3.0 to 4.0 t, 4, 5 or 6-fold screening, hot aggregate storage of 60 to 130 t, a loading silo of up to 517 t and RAP addition of up to 40%.
  • Application fit: transportable plants suited to semi-mobile or stationary deployment, for contractors who move between road projects.

View Benninghoven TBA plants

2. Benninghoven ECO Asphalt Mixing Plants

  • Confirmed specification: 4 models with mixing capacities of 100 to 320 t/h, mixer sizes of 2.0 to 4.0 t, hot aggregate storage of 17 to 87 t, a loading silo of up to 400 t and RAP addition of up to 70%.
  • Application fit: stationary production with transport-optimised, standard container-sized modules for fast relocation to new sites.

View Benninghoven ECO plants

3. Benninghoven RPP Asphalt Mixing Plants

  • Specification confirmed: 3 models with mixing capacity of 240 to 400 t/h, mixers with capacities from 4.0 to 5.0 t, 6-stage screening, storage of hot aggregates from 80 to 320 t, a loading silo of 1,100 t and RAP proportion up to 100%.
  • Application field: plants with high production output for producers wishing to maximise recycled material content. According to Benninghoven, the RPP series is more economical and environmentally friendly because of reuse of RAP.

View Benninghoven RPP plants

Asphalt manufacturing planning for a roads program?

Please send us the tons, paving rate, haul distances, and the amount of RAP that you will recycle. We will suggest the plant to be used.
REQUEST AN ASPHALT PLANT PROPOSAL

Matching the Plant to the Paving Train

It is because all the equipment involved, including the plant, trucks, paver, and rollers, are part of one process. The speed of the plant compared to that of the paver determines how cold or hot the materials will be when placed into the trucks. If it’s too fast or slow, it stops and joints will be created. Size the plant based on the paving rate and then trucks based on the haul.

UAE Conditions for Asphalt Plants

  • High temperature: Hot surroundings increase load on motors, burners, and control panels. Ensure electrical rooms are properly ventilated and clean cooling units.
  • Dust: Dust is created during the process of aggregate drying and proper filtration and maintenance are crucial for plant and its neighborhood.
  • Paving at night: Paving is done at night because of summer hours; therefore, proper planning is necessary.
  • Consistent material supply: Proper grading and moisture content of aggregates simplify plant operation.

Asphalt Plant Specification Methodology

  • Step 1 - Determine the annual/peak throughput and the mixes required.
  • Step 2 - Specify the period spent by the asphalt plant on each site.
  • Step 3 - Specify a target reclaimed asphalt pavement rate (RAP rate).
  • Step 4 - Specify the capacity of the loading silo according to the truck queue/paver stop times.
  • Step 5 - Specify the site facilities requirements regarding power, diesel and bitumen.
  • Step 6 - Specify commissioning, operator training and parts support prior to delivery.

Why Consider GENAVCO for Your Asphalt Plants

  • Benninghoven range: transportable, relocatable and high-RAP plants from one maker. See Benninghoven asphalt plants.
  • Support from design to commissioning: GENAVCO's specialists support each stage from design adaptation to commissioning and training.
  • Member of Juma Al Majid Group from 1967: A trusted UAE company with ISO 9001 accreditation.

Common Asphalt Plant Mistakes

  • Sizing for the peak day only: a plant that runs half-empty for most of the year costs more per tonne.
  • Ignoring relocation time: moving a stationary plant between projects can cost weeks.
  • RAP planning without RAP supply: for recycling there must be a consistent supply of RAP millings.
  • Small size of loading silo: without finished mix storage capacity, every truck problem halts production.
  • Plant out of step with paving: mismatched output leaves mix cooling or pavers waiting.

Frequently Asked Questions

What is an asphalt plant?

A facility which dries and heats the aggregate, separates it into fractions, weighs it along with the bitumen and fillers, and produces hot asphalt.

How do I select the capacity of an asphalt plant?

Select it in terms of tonnes per hour in accordance with the paving speed and number of gangs, and then account for haul distances and other factors.

What does RAP mean in an asphalt plant?

RAP means Reclaimed Asphalt Pavement which is obtained by milling old roads. Plants that are meant for these can use a portion of this material in their new mixes. According to Benninghoven, up to 40% for TBA, 70% for ECO and 100% for RPP plants is possible.

Can an asphalt plant be relocated?

Yes, provided the plant is meant to be relocated. Benninghoven TBA plants are relocatable to semi-mobile or stationary plants while ECO plants use modular construction on standard containers for relocation.

Ready to Develop Your Asphalt Plant?

Having the right asphalt plant will ensure that the pavement train has continuous supply of the right mix at the right temperature. The company, GENAVCO supplies Benninghoven asphalt plants throughout the UAE. Read why better asphalt production and paving makes better roads.

Tell us your tonnage, sites and recycling targets. We will recommend the right plant and price it properly.

Serving Dubai, Abu Dhabi, Sharjah, Al Ain and the wider UAE.

REQUEST AN ASPHALT PLANT PROPOSAL

More Blogs

Hamm
02Jul

Soil Compactors and Plate Compactors: Key Differences Explained

Godrej
02Jul

How to Choose the Right Forklift for Warehouse Operations

Crown
02Jul

Why Pallet Racking Systems Are Essential for Modern Warehouses